New Huyndai CNC

Specs, Picture of front

On 1/11/2019

Received chip conveyor.

On 1/16/2019

Received the machine.

On 1/17/2019

Connected electrical power by Access.

On 1/25/2019

According to Octavio:

Installation report.

Tuesday 1-22-2019 : The Technician start level the machine

Wednesday 1-23-201: Connecting chip conveyor and the rest of connectors and lubricants 

Thursday 1-24-2018: Finish all installation, install the existing programs (From the other CNC) and training and instruct the operators

Ordered new set of tool holders from Bass Tools

On 3/11/2019

Verified that all the tools were received. Machine is ready to run.

Traning class was done.